Penihana Stage 4
19-27 O’Neills Road, Swanson, Auckland
Hick Bros is currently in the final stage that will wrap up the approx. 5-year long project known as the Penihana Development. In addition to the 54 proposed lots works will also include upgrading the existing intersection of Pooks Road and O’neills Road, as well as the newly constructed Mettam Drive.
Penihana Stage 4
Penihana Stage 4
Earthworks & Civils (July 2018 – July 2019)
BUDGET
$2.5M
PROPOSED LOTS
54
CUT/FILL TO DATE
3617 M3
Scope of Works
Sediment and Erosion Control
Stripping of Topsoil
Excavation of all materials met and compaction as certified fill material
Clearing of Vegetation
Co-ordinate works adjacent to existing utilities
Soil Stabilization of all Earthworks
Construction of Concrete Footpaths, Right of Ways, and Kerbs
Construction of level 1 roads consisting of subgrade prep, laying of base course, final surfacing and kerbs
Installation of network utilities in trenches