ARRAN POINT

MILLWATER, AUCKLAND
BULK EARTHWORKS

Bulk Earthworks have been taking place at our Millwater site since November 2015. The largescale earthworks cover around one million cubic meters of the Arran Hill site and include retaining structures, palisade piles and shear keys. The site has been no easy feat for our team; sensitive overlaying soils and proximity to the Orewa Estuary has continually tested us and our machines within our tight time frame.

ARRAN POINT

Precinct 5 – Arran Hill
November 2015 – April 2018

project6

EARTHMOVING

1,200,000 M3

SHEAR KEY/UNDERCUT QUANTITIES TO DATE

300,000 M3

REMAINING CUT INCLUDING SP

170,000 M3

PALISADE PILES COMBINED LINEAL LENGTH

4.5km

project8
Top of the World

Workers pose at the top of a reinforced eath wall

September 2016,

Milestones here

October 2016,

Milestones here

November 2016,

Milestones here

December 2016,

Milestones here

January 2017,

Milestones here

February 2017,

Milestones here

 